Power Up Procedure
From athena
- Turn everything off downstream
- Turn on main breaker
- Make sure you set the compute nodes breakers off
- Rack 3 -- 21,22,39
- Rack 4 -- 4,3,45
- Rack 5 -- 10,9,52
- Rack 6 -- 16,15,28
- Make sure you set the RC unit breakers off
- RC1A -- 56
- RC2A -- 55
- RC4A -- 49
- RC5A -- 44
- Make sure you set the UPS breaker off
- Flip the UPS breakers off for rack 1 and 2
- make sure the Clariion RAID controller is also turned off (take a picture)
- Check chiller, open valves if needed
- Switch disconnect on the wall to ON
- Look through rear main PDU access panel to see if the input breaker is off/on/intermediate
- If not ON, Open locked rear PDU door and reset the EPO circuit:
-
- At lower left of open rear door, press Test/Armed switch to "Test"
- Close rear door, open circuit breaker access door,
- Cycle breaker down (off) then up (on).
- Power up RC units (bkrs 44,49,55,56)
- Power up UPS (breaker 46,48)
- Verify UPS operation by its front panel
- Use UPS front panel (->Control->"Turn UPS output ON"->Yes) to activate its output.
- At rear of UPS, turn on breakers for Rack 0, verify water sensor power.
- At rear of UPS, turn on breakers for Rack 1 and Rack 2
- Power up Athena0 and Athena9
- Check RC units to verify cooling is happening.
-
- Close room doors.
- Follow Polyserve Power Up Procedure (Jan 22nd: not A6, A7, A8)
- Return to rear of main PDU.
- Open rear panel.
- Verify that both lamps to right of Test/Armed switch are off
- (if "Tripped" lamp is on, correct that Emergency Off condition)
- Set switch from "Test" to "Armed"
- Close and lock rear panel
- Power up the compute rack breakers (3,4,9,10,15,16,21,22,28,39,45,52)
- Power up the nodes if necessary (r4 n16 requires "F1" key .. twice)
- Close all rack doors
- Check the nodes have booted properly by using Ganglia or "cluster-ps" command
- Email users...